Thursday, April 3, 2008

Sheetrock phase complete!!!

I took a solo trip out to the house yesterday and found a few nice suprises. First off, the driveway was poured and the path up to the stairs was done. Then I noticed the gutters had all been installed (not a big item, but nice to see.) Then I went inside and saw that they had finished painting inside which was the last step in the sheetrock phase. as I wandered through the house, I got to the garage and found all of our cabinets and doors had been delivered.

That means we have moved on to the "Interior Trim Phase" that includes:
  • Electrical Trim Complete including Light Fixtures
  • Install Cabinets and Doors
  • Hard Surfaces Complete (Vinyl, Tile, Laminate, etc.)
  • Plumb Trim Complete
  • Heat Trim Complete
  • Fireplace Trim Complete
  • Mirrors and Shower Doors Installed
  • Wire Shelving Installed
  • Carpet Installed
We can't wait for everyone to see it all in person.

1 comment:

Oergel said...

Wow! When's the move-in date again? It looks like your crew is well ahead of schedule. Love the colors - very nice.